Program of Works in Quantity Surveying - Egbodo Benjamin

Breaking

Egbodo Benjamin — Entrepreneur • Cultural Curator • Creative Leader
Egbodo Benjamin

Founder & CEO of This Is Hip Hop HQ — a four‑time award‑winning global platform dedicated to empowering independent artists, preserving authentic hip‑hop culture, and amplifying creative voices across Africa and beyond.

Certified Project Manager, Fellow of the International Trade Council, and FOYA Africa Awards 2024 nominee for “Social Founder of the Year (Under 30).”

A dynamic blogger, youth advocate, and cultural curator committed to inspiring resilience, creativity, leadership, and purpose‑driven impact.

“Driven by vision, guided by discipline, and fueled by purpose — Benjamin continues to redefine excellence and shape the future of African creativity.”

Saturday, November 29, 2025

Program of Works in Quantity Surveying

Why Every QS Needs This Tool in Their Arsenal

If there’s one universal law in construction, it’s this: anything without a timeline will eat your budget alive. Contractors know it, clients feel it in their souls, and quantity surveyors? We’re stuck in the courtroom of cost versus time, defending our valuations like attorneys fighting for justice.


Welcome to the Program of Works—the unsung hero that keeps construction from turning into a freestyle disaster.

In hip-hop terms, this is the “master schedule,” the project’s version of a release calendar. Without it, even the dopest plans fall apart like a rushed mixtape rollout. With it, though? Everything hits in rhythm.

Let’s break it down like a classic Boom Bap beat.


What a Program of Works Really Is

Legal definition-ish?
It’s a contractual project timeline—a documented schedule that outlines the order, duration, and relationship between all construction activities. Once accepted, it becomes a binding reference in claims, valuations, disputes, and progress assessment.

Practical QS definition?
It’s that sacred map that saves your professional reputation when the site team swears “we’re on schedule” but the building still looks like a sketch.

Most times, it shows up as a Gantt chart. Sometimes it’s a bar chart. Whatever the flavor, it’s the project’s heartbeat.


Core Components You Should Never Skip

You wouldn’t drop a rap verse without flow, bars, and delivery. Same thing here—your Program of Works needs its essentials:

✔ Activity Breakdown

From site clearance to finishes—everything gets listed. No ghost activities. No hidden verses.

✔ Start & Finish Dates

This is your timeline—your statute of limitations for every task.

✔ Logical Sequencing

Like hip-hop beefs, some things just can’t happen out of order. Foundations before walls. Walls before roofing.

✔ Milestones

Trophies. Achievements. “Structure completed,” “roof installed,” “handover readiness,” etc.

✔ Resource Scheduling

Labor, materials, equipment—this is where the QS checks if the contractor plans to “do a Drake album with no features” or actually bring a team.

✔ Critical Path

The legal “red line.” Any delay here = the whole project feels it. No negotiation.


Why Quantity Surveyors Treat the Program Like Gospel

As a QS, the Program of Works is the closest thing you have to financial X-ray vision.

Here’s why it’s clutch:

1. Cash Flow Planning

You don’t “estimate” payments; you legally justify them. The program gives your forecast structure.

2. Interim Valuations

You value what’s actually done—not vibes. Program of Works keeps everyone honest.

3. Claims & Variations

Extensions of time? Loss & expense? Delays by client?
This is where you pull out the program like court evidence.

4. Contract Administration

Whether you’re dealing with FIDIC, JCT, NEC, or local contract laws, the program helps enforce timelines.

5. Risk Management

If the program starts slipping, you can predict cost impacts before they blindside the client.

It’s basically the QS version of “reading the future.”


Sample Housing Project Schedule

Picture this like the tracklist of a classic album—each activity is a song, flowing into the next.

Activity Duration Start Finish Dependencies
Site Clearance 2 weeks Week 1 Week 2 None
Foundation Works 4 weeks Week 3 Week 6 Clearance
Structural Frame 6 weeks Week 7 Week 12 Foundation
Roofing & Externals 6 weeks Week 13 Week 18 Frame
Internal Finishes 6 weeks Week 19 Week 24 Roofing

With this, a QS can:

  • Forecast monthly payments
  • Flag risks
  • Track actual vs planned progress
  • Advise the client when the contractor starts moving suspiciously slow

Common Challenges (Because Construction Never Behaves)

❌ Bad Data

A poorly prepared program is like a mumble rapper trying to battle J. Cole—no chance.

❌ Weather & Supply Chain Drama

Rain, late materials, global price shocks—real QS PTSD.

❌ Poor Integration

Procurement schedules not matching timelines?
Contractor working on vibes?
Red flag.

❌ Communication Gaps

QS, PM, contractor, architect—everyone needs to talk. Not WhatsApp-voice-note talk, actual documentation-level talk.


Best Practices for Quantity Surveyors

Some QSs treat the program like decoration. Not you. Not on your site.

✔ Collaborate Early

Be in the room when the program is born.

✔ Update Frequently

Programs aren’t tattoos; they change.

✔ Use Technologies

MS Project, Primavera P6—whatever keeps the contractor accountable.

✔ Link Time to Cost

Real QS work happens here.

✔ Keep Records Like a Lawyer

Because when claims come, you’ll need receipts. Literally.


Final Thoughts

The Program of Works is more than a timeline—it’s the law book, the mixtape, the compass, and the financial steering wheel of any construction project. It turns numbers into narratives and deadlines into deliverables.

A QS without a program is like a DJ without decks. Chaos. Noise. No rhythm.
But with it? You’re orchestrating a masterpiece from foundation to finishes.

And hey—if this helped you, share the article, spread the knowledge, and tell fellow builders to plug into more real talk.